Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Termovalorizzatore Firenze
Issues
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Termovalorizzatore Firenze
Investments: EIB 20150044
Client:
Support: Loans
Country: Italy
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2015/06/PR
Date Filed: April 22, 2015
Date Closed: May 13, 2015
Description
Complaint Stages
Filing
April 22, 2015
Filing
Status:
Start Date: April 22, 2015
Registration
April 22, 2015 -
April 28, 2015
Registration
Status: Closed With Output
Start Date: April 22, 2015
End Date: April 28, 2015
Eligibility
April 28, 2015 -
May 13, 2015
Eligibility
Status: Closed With Output
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
May 13, 2015
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
Ufficio Acquisti | 1 | Individual |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Termovalorizzatore Firenze 2 | EIB CM | Italy | 21/05/2015 | Closed Without Outputs |