Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
TES - Thermal Power Plant Sostanj
Issues
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2011/02
Date Filed: Feb. 28, 2011
Date Closed: March 7, 2019
Status: Closed With Outputs
Complaint Stages
Filing
Feb. 28, 2011
Filing
Status:
Start Date: Feb. 28, 2011
Registration
Feb. 28, 2011 -
Feb. 28, 2011
Registration
Status: Closed With Output
Start Date: Feb. 28, 2011
End Date: Feb. 28, 2011
Eligibility
Feb. 28, 2011 -
Dec. 6, 2012
Eligibility
Status: Closed With Output
Start Date: Feb. 28, 2011
End Date: Dec. 6, 2012
Dispute Resolution
Not Undertaken
Compliance Review
Dec. 6, 2012 -
March 7, 2019
Compliance Review
Status: Closed With Output
Start Date: Dec. 6, 2012
End Date: March 7, 2019
Has Compliance Report: Yes
Non-Compliance Found: No
Monitoring
March 7, 2019
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party
Closed
March 7, 2019
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
CEE Bankwatch Network | 41 | International CSO |
Focus Association for Sustainable Development, Environmental Legal Service | 2 | Local CSO |