Uttar Pradesh Major District Roads Improvement Project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Uttar Pradesh Major District Roads Improvement Project
Investments: ADB 3386-IND
Client:
Support: Loans
Country: India
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: April 1, 2021
Date Closed: June 3, 2021
Complaint Stages
Filing
April 1, 2021
Filing
Status:
Start Date: April 1, 2021
Registration
April 1, 2021 -
May 18, 2021
Registration
Status: Closed With Output
Start Date: April 1, 2021
End Date: May 18, 2021
Eligibility
May 18, 2021 -
June 3, 2021
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
June 3, 2021
Timeline