Vasilikos-Western Nicosia Conveyor Water Supply
Issues
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Vasilikos-Western Nicosia Conveyor Water Supply
Investments: EIB
Client:
Support: Loans
Country: Cyprus
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2015/09/PR
Date Filed: May 20, 2015
Date Closed: June 4, 2015
Description
Complaint Stages
Filing
May 20, 2015
Filing
Status:
Start Date: May 20, 2015
Registration
May 20, 2015 -
May 20, 2015
Registration
Status: Closed With Output
Start Date: May 20, 2015
End Date: May 20, 2015
Eligibility
May 20, 2015 -
May 27, 2015
Eligibility
Status: Closed With Output
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
June 4, 2015
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
Friends of Akamas | 1 | Local CSO |