Vasilikos-Western Nicosia Conveyor Water Supply | Accountability Console
Complaints IAMs Register Login

Loading...

Vasilikos-Western Nicosia Conveyor Water Supply

Issues

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 965

Browse Complaints

Project

Name: Vasilikos-Western Nicosia Conveyor Water Supply

Investments: EIB

Client:

Support: Loans

Country: Cyprus

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2015/09/PR

Date Filed: May 20, 2015

Date Closed: June 4, 2015

Status: Closed With Outputs Outside Process

Description

The letter received from the Friends of Akamas raised some concerns whether the conveyor of water from Vasilikos desalination to Nicosia is indeed the best option. The letter does not raise any specific complaints. The EIB-CM forwarded the letter to the EIB operational services so that the information provided by the complainant is taken into consideration in the project appraisal.

Complaint Stages

Filing

May 20, 2015

Filing

Status:

Start Date: May 20, 2015

Registration

May 20, 2015 -

May 20, 2015

Registration

Status: Closed With Output

Start Date: May 20, 2015

End Date: May 20, 2015

Eligibility

May 20, 2015 -

May 27, 2015

Eligibility

Status: Closed Without Output

Explanation: Forwarded to other body within bank; Inadequate information, Early-stage project

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

June 4, 2015

Timeline

Involved Groups

Name Complaints Group Type
Friends of Akamas 1 Local CSO