Visayas Base-Load Power Project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Project
Name: Visayas Base-Load Power Project
Investments: ADB
Client:
Support: Loans
Country: Philippines
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: SPF-2011-03-01-0035 & 2011/1
Date Filed: Feb. 28, 2011
Date Closed: Nov. 13, 2017
Status: Closed With Outputs
Complaint Stages
Filing
Feb. 28, 2011
Filing
Status:
Start Date: Feb. 28, 2011
Registration
Feb. 28, 2011 -
March 1, 2011
Registration
Status: Closed With Output
Start Date: Feb. 28, 2011
End Date: March 1, 2011
Eligibility
March 1, 2011 -
March 17, 2011
Eligibility
Status: Closed With Output
Start Date: March 1, 2011
End Date: March 17, 2011
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not desired by complainant, Complainant chose not to have dispute resolution
Compliance Review
March 17, 2011 -
April 11, 2012
Compliance Review
Status: Closed With Output
Start Date: March 17, 2011
End Date: April 11, 2012
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
April 11, 2012 -
Nov. 13, 2017
Monitoring
Status: Closed With Output
Start Date: April 11, 2012
End Date: Nov. 13, 2017
Closed
Nov. 13, 2017
Timeline
Commitments