Warsaw Ring Road, Poland | Accountability Console
Complaints IAMs Register Login

Loading...

Warsaw Ring Road, Poland

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Warsaw Ring Road

Investments: EIB

Client:

Support:

Country: Poland

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2011/01

Date Filed: Feb. 7, 2011

Date Closed: Nov. 14, 2011

Status: Closed With Outputs

Description

The complaint concerns the impact of section S2 of the Warsaw Ring Road project, that it i) will expose the buildings close to the expressway to noise and pollution ii) that the sewage and wastewater drainage of the project has not been properly planned and iii) that sewage water will be conducted into agricultural irrigation channels which could pollute surface and groundwater, as well as the soil. Moreover, the preparation of the land levelling for the project has caused flooding in the residential areas, which has caused serious damage and that no evaluation of vibration impacts of heavy trucks passing close to the houses has been carried out; heavy truck traffic risk damaging the buildings bordering the expressway. In general and overall the complaint concerns a total lack of public consultation and neglect of the community’s opinion on the location of the project.

Complaint Stages

Filing

Feb. 7, 2011

Filing

Status:

Start Date: Feb. 7, 2011

Registration

Feb. 7, 2011 -

Feb. 22, 2011

Registration

Status: Closed With Output

Start Date: Feb. 7, 2011

End Date: Feb. 22, 2011

Eligibility

Closed With Output

Eligibility

Status: Closed With Output

Explanation: Mechanism deemed involvement unnecessary

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage; Unknown

Compliance Review

Feb. 22, 2011 -

Nov. 14, 2011

Compliance Review

Status: Closed With Output

Explanation: Case closed in earlier stage

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party

Closed

Nov. 14, 2011

Timeline

Involved Groups

Name Complaints Group Type
Stowarzysyenie Sasiedzkie Zaluski Stasin 1 Local CSO

Related Complaints

Project IAM Country Date Filed Status
Warsaw Ring Road, Poland EIB CM Poland 13/07/2010 Closed With Outputs