Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

111 Results

Showing Only IDB Independent Consultation and Investigation Mechanism (Show All Results)

Top Results By:

Show All

  1. Complaint > La Paz Storm Drainage Program II

    Eligibility: Issuance of Eligibility Memorandum

    ...Request was registered on May 16, 2014, upon receipt of confirmation as to certain matters from the Requester. 1.2 The Requester has requested that all personal information remain confidential due to fear of retaliation. In accordance with Section 33 of the ICIM Policy, all personal information, as well as some details contained in the Request that could otherwise reveal the Requester’s identity, will not be disclosed. 1.3 The Requester is the owner ...

    IDB Independent Consultation and Investigation Mechanism - Bolivia - 2014
  2. Complaint > Mario Covas Rodoanel Project - Northern Section

    Eligibility: Eligibility Memorandum Public Disclosure

    ...Requesters communicated with the MICI to submit a new Request from the same three Requesters and regarding the same issues raised in Request MICI-BID-BR-2016-0109, claiming their concerns had not been resolved. The new Request was registered on 22 March 2017 under MICI-BID-BR-2017-0118. The Requesters asked the Mechanism to keep their identity confidential. 2.3 In the Request, the Requesters allege they are currently being affected by road cons...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2017
  3. Complaint > Serra do Mar and Atlantic Forest Mosaics System Socioenvironmental Recovery Program

    Management Response: Submission of the final document to the Board of Executive Directors for consideration

    ...Request was processed and transferred to the Project Ombudsperson once the ICIM came into effect in September of 2010. On October 8, 2010, the Request was declared ineligible for the Consultation Phase. 2.3 The Request was then transferred to the Compliance Review Phase and on December 15, 2010, the former Panel Chairperson determined that the Request was eligible for a Compliance Review. In December 2010, another interested Requester, Mr. Dauro Marcos do Prado, President of ...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2014
  4. Complaint > Program to Improve Highway Corridors in Paraguay

    Eligibility: Issuance of Eligibility Memorandum

    ...Request was sent to MICI by Professors Kim Hill and Magdalena Hurtado on behalf of the Ache community and some of their leaders. The Request alleges that the Ache have suffered harm and will continue to do so due to the Bank’s failure to enforce provisions in the Loan Agreement that were meant to safeguard their rights to ancestral lands. The Request also refers to earlier forceful evictions and to ILO‐ Convention 169 that the Requesters allege supports the Ache community’s claims to the dispute...

    IDB Independent Consultation and Investigation Mechanism - Paraguay - 2011
  5. Complaint > Mario Covas Rodoanel - Northern Sections 1 and 2 (2011)

    Eligibility: Issuance of Eligibility Memorandum

    ...Requester’s name and contact information for the Requester information are recorded. are available. Project and operation at issue Fulfilled Rodoanel Mário Covas Project – have been identified. Northern Section 1 (BR-L1296) and 2 (BR-L1302). The Requester resides in the Fulfilled The Request...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2011
  6. Complaint > El Dorado International Airport

    Eligibility: Issuance of Eligibility Memorandum

    ...Request is eligible for the Consultation Phase. I. Request Summary 1.1 On 12 August 2011, the Independent Consultation and Investigation Mechanism (ICIM)1 received a Request from the organization COMUNIDAD (Comunidades Unidas Macroproyecto Aeropuerto El Dorado) (the Requesters), on behalf of residents of Localidad Novena de Fontibón. The Requesters are represented by Ms. Gloria Cecilia Molina Villamarín (Representative).2 The Request describes the ...

    IDB Independent Consultation and Investigation Mechanism - Colombia - 2011
  7. Complaint > Multiphase Development Infrastructure Program: Support Production in Entre Rios

    Monitoring: Third Monitoring Report

    ...Requester with respect to the monitoring measures. Monitoring reports shall be issued at least semi-annually for so long as the Project Ombudsperson deems appropriate. Monitoring protocols and reports shall be made public via the Registry. The Project Ombudsperson will notify the President, Board (and the Donors Committee, in the case of a MIF-funded operation), the Requester, and other relevant parties of the results of its periodic monitoring exercises a...

    IDB Independent Consultation and Investigation Mechanism - Argentina - 2015
  8. Complaint > Northern Corridor Highway Improvement Program - Santa Barbara - Rurrenabaque and San Buenaventura

    Appraisal: Issuance of Assessment Report

    ...Request On 15 March 2011, individual citizens, nongovernmental organizations, and neighborhood groups 1 (the Requesters) submitted to the Independent Consultation and Investigation Mechanism (ICIM) 2 a Request related to the potential environmental and social impacts of the planned building of a bridge connecting Rurrenabaque and San Buenaventura in Bolivia (the bridge project). Some of the Requesters have asked that the ICIM maintain confidentiality in dealing with and handling this Request. Th...

    IDB Independent Consultation and Investigation Mechanism - Bolivia - 2011
  9. Complaint > Low-Income Neighborhood Improvement Program - Habitar Brasil

    Monitoring: Third Monitoring Report

    ...Requesting families Requester in her new home MICI photograph MICI photograph 5 Low-income Neighborhood Case Improvement Program Habitar BR-MICI004-2011 ...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2017
  10. Complaint > Alto Maipo Hydroelectric Power Project

    Filing: Request Receipt

    ...President of Ecosistemas and Director of International Rivers, traveled 1 to Washington, DC in September 2015 to meet with representatives of the financial institutions headquartered in the United States that are financing the PHAM (IDB, IFC, and the guarantor bank of the U.S. government, OPIC). This meeting was requested because of the numerous intractable concerns about the risks posed by the PHAM that have not been seriously addressed by the Co...

    IDB Independent Consultation and Investigation Mechanism - Chile - 2017
  11. Complaint > Low-Income Neighborhood Improvement Program - Habitar Brasil

    Monitoring: First Monitoring Report

    ...Requester with respect to the monitoring measures. Monitoring reports shall be issued at least semi- annually for so long as the Project Ombudsperson deems appropriate. Monitoring protocols and reports shall be made public via the Registry. The Project Ombudsperson will notify the President, Board (and the Donors Committee, in the case of a MIF-funded operation), the Requester, and other relevant parties of the results of its periodic monitor...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2015
  12. Complaint > Support for the Sustainable Development of the Interior

    Filing: Request received by Executive Secretariat

    From: Daniel Peplow [mailto:dpeplow@uw.edu] To: Suriname Country Office Cc: MICI; Daniel Peplow Subject: SIHF Petition_ICIM_Wayana_Suriname Marco Carlo Nicola Inter-American Development Bank Country Office Paramaribo, Suriname Dear Representative Nicola. The Suriname Indigenous Health Fund (SIHF) on behalf of the Wayana people (see attached letter requesting assistance) is writing to address the very difficult situation of the indigenous people who live in the villages of Puleowime (Apetina) as...

    IDB Independent Consultation and Investigation Mechanism - Suriname - 2013
  13. Complaint > Multiphase Development Infrastructure Program: Support Production in Entre Rios

    Appraisal: Issuance of Assessment Report

    ...Request was received by the Ombudsperson on 20 September 2010. The objective of the assessment process was: (a) to gather further information on the claim submitted to the ICIM and its possible ramifications for project implementation, and (b) to explore whether a dialogue phase should be initiated and flexible, consensus‐oriented methods used to address the substance of the Request. Primary concerns of Requesters: (i) lack of access to information; (ii) irregularities in the consultation proces...

    IDB Independent Consultation and Investigation Mechanism - Argentina - 2011
  14. Complaint > Termoelectrica del Golfo Project

    Filing: Request received by Executive Secretariat

    Translation from the Original Request in Spanish ELLIS J. JUAN. AVENIDA PASEO DE LA REFORMA NO. 222, 11TH FLOOR. COLONIA JUÁREZ, DELEGACIÓN CUAUHTÉMOC, MEXICO CITY, FED. DIST. POSTAL CODE 6600. TEL. (55) 9138-6200DR. INTER-AMERICAN DEVELOPMENT BANK (IDB). MEXICO CITY, FED. DIST., OFFICE. TO THE ATTENTION OF THE OFFICE OF THE MICI. INDEPENDENT CONSULTATION AND INVESTIGATION MECHANISM OFFICCE. (sic) INTER-AMER...

    IDB Independent Consultation and Investigation Mechanism - Mexico - 2011
  15. Complaint > Porce III Hydroelectric Power Plant

    Filing: Request Receipt

    ...president of the Bramadora community action board, informed him of the following: RE: Response to your request regarding mining activity in the area of influence of the Porce III hydroelectric project With respect to the request made in your official letter of September 1, 2003, with internal filing number , addressed to the head of the project area, we inform you that Empresas Públicas de Medellín (EPM) sent the authorization to the fourth brigade for the storage of explosive mater...

    IDB Independent Consultation and Investigation Mechanism - Colombia - 2015
  16. Complaint > Sao Jose dos Campos Urban Structuring Program

    Compliance Report: Publication of Panel Report

    ...request of any Executive Director, upon written request to the Office of the Secretary at least three business days in advance of the date of the respective meeting. 15 The original Request is available in the MICI Public Registry, which can be accessed from the electronic links section of this document. 16 These organizations have been providing support to the Central de Movimentos Populares and to the Requesters throughout the MICI’s processing of the Request, especially during the...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2017
  17. Complaint > Sao Jose dos Campos Urban Structuring Program

    Compliance Report: Publication of Panel Report

    ...request of any Executive Director, upon written request to the Office of the Secretary at least three business days in advance of the date of the respective meeting. 15 The original Request is available in the MICI Public Registry, which can be accessed from the electronic links section of this document. 16 These organizations have been providing support to the Central de Movimentos Populares and to the Requesters throughout the MICI’s processing of the Request, especially during the...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2017
  18. Complaint > Reventazon Hydroelectric Power Project

    Eligibility: Eligibility Memorandum Public Disclosure

    ...Request against the eligibility criteria established in its Policy to determine whether or not the Request is eligible and whether it can be accepted for processing. This eligibility determination is neither an assessment of the merits of the Request or the issues raised, nor a determination of the IDB Group’s compliance or noncompliance with its Relevant Operational Policies. If the Request is declared eligible, the process will begin for the phase selected by the Requesters; otherwise, the Req...

    IDB Independent Consultation and Investigation Mechanism - Costa Rica - 2018
  19. Complaint > Ituango Hydropower Plant

    Eligibility: Eligibility Memorandum Public Disclosure

    ...Request with respect to the criteria established in its Policy, to determine whether the Request fulfills those criteria and may therefore be accepted for processing. This analysis is not an evaluation of the merits of the Request nor of the issues raised therein; neither is it a determination of the IDB Group’s compliance or noncompliance with the Relevant Operational Policies. If the Request is declared eligible, it is transferred to the Phase requested by the Requesters; for Requests that are...

    IDB Independent Consultation and Investigation Mechanism - Colombia - 2018
  20. Complaint > Tietê Várzea Program

    Eligibility: Eligibility Memorandum Public Disclosure

    ...Request. Telephone call with Requesters concerning the Request and the MICI 1 August process. Allowance of a maximum period of 10 business days for the Requesters 4 August to present additional information required to process the Request. 17 August Receipt of additional information requested of the Requesters. 22 August Registration of ...

    IDB Independent Consultation and Investigation Mechanism - Brazil - 2017