AD Hydro Power Limited-01/Himachal Pradesh | Accountability Console
Complaints IAMs Register Login

Loading...

AD Hydro Power Limited-01/Himachal Pradesh

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 120

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Project

Name: AD Hydro Power Limited-01/Himachal Pradesh

Investments: IFC 11632

Client:

Support: Loans

Country: India

Complaint

IAM: Compliance Advisor/Ombudsman (CAO)

ID: india-ad-hydro-power-limited-01himachal-pradesh

Date Filed: Oct. 1, 2004

Date Closed: March 31, 2008

Status: Closed With Outputs

Complaint Stages

Filing

Oct. 1, 2004

Filing

Status:

Start Date: Oct. 1, 2004

Registration

Not Undertaken

Registration

Status: Not Undertaken

Start Date: None

Eligibility

Oct. 1, 2004 -

March 24, 2005

Eligibility

Status: Closed With Output

Start Date: Oct. 1, 2004

End Date: March 24, 2005

Dispute Resolution

March 24, 2004 -

March 23, 2005

Dispute Resolution

Status: Closed With Output

Start Date: March 24, 2004

End Date: March 23, 2005

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

March 23, 2005 -

March 31, 2008

Monitoring

Status: Closed With Output

Start Date: March 23, 2005

End Date: March 31, 2008

Closed

March 31, 2008

Timeline

Commitments

Type Category Description Status
Agriculture Livelihoods Apple Crops Incomplete
Agriculture Livelihoods Access to and impact on pastureland Incomplete
Agriculture Livelihoods Availability of potato seeds Incomplete
Capacity Building Social Support Community Capacity Development Due To Land Acquisition Incomplete
Capacity Building Social Support AIDS education Incomplete
Cash Compensation Compensation for crops Accomplished
Cash Compensation Compensation For Land Acquisition Accomplished
Cash Compensation Compensation for Water Disturbances Incomplete
Collective Compensation Compensation Payment to Local Governments Incomplete
Community Safety Social Support Reservoir safety Incomplete
Community Safety Social Support Risk due to natural hazards (earthquakes , forest fires, landslides, etc.) Accomplished
Community Safety Social Support Women’s safety and security Accomplished
Community Safety Social Support Decreased Public Health Impacts from Vehicle Dust/Traffic Accomplished
Consultation (non-FPIC) Consultation Public Consultation and Disclosure Plan Accomplished
Cultural Heritage Cultural Heritage Religious sentiments Incomplete
Education Social Support School Construction Incomplete
Employment conditions Labor Employee Health and Safety Incomplete
Employment conditions Labor Influx of labour force in the area Incomplete
Employment Opportunities Livelihoods Employment Opportunities Incomplete
Environmental Protection Environment Impact on fisheries Incomplete
Environmental Protection Environment Fuel wood for force Accomplished
Environmental Protection Environment Impact on wildlife habitat and flora Incomplete
Environmental Remediation Environment Noise pollution and Blasting Incomplete
Environmental Remediation Environment Forest Incomplete
Environmental Studies Environment Impact Assessment of 185 km Transmission Line from switchyard at Prini to Nalagarh Incomplete
Health Social Support Hospital Construction and Equipment Accomplished
Information disclosure Consultation Availability of previous ESIA reports Accomplished
Infrastructure Social Support Village Electricity and Lighting Accomplished
Infrastructure Social Support Public access to project roads Accomplished
Infrastructure Social Support Roadway Construction Accomplished
Job Training Livelihoods Livelihood Restoration Due To Land Acquisition Accomplished
Monitoring Project Impacts Monitoring Implementation of Environmental Action Plan Incomplete
Monitoring Remedies Monitoring Monitoring Remedies Of Land Acquisition Actions Incomplete
Other Livelihoods Livelihoods Impact on local culture and tourism Incomplete
Other Social Support Social Support Recreation Grounds Accomplished
Project-Level Grievance Mechanism Grievance Mechanism Recourse/ Compliance Mechanism Accomplished
Sanitation Social Support public conviences Accomplished
Sanitation Social Support Muck Disposal Incomplete
Sanitation Social Support Solid waste disposal Incomplete
Sanitation Social Support Waste water treatment Incomplete
Water Social Support Contingency Water Supplies Accomplished
Water Social Support Drinking & Irrigation Water Accomplished