Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Human rights
Description: Complaint frames concerns using the language of human rights violations.
Complaints with this Issue: 66
Indigenous peoples
Description: Complaint raises concerns about impacts on indigenous or traditional communities.
Complaints with this Issue: 89
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit
Investments: WB
Client:
Support: Loans
Country: Nepal
Complaint Stages
Filing
Oct. 24, 1994
Filing
Status:
Start Date: Oct. 24, 1994
Registration
Oct. 24, 1994 -
Nov. 3, 1994
Registration
Status: Closed With Output
Start Date: Oct. 24, 1994
End Date: Nov. 3, 1994
Eligibility
Nov. 3, 1994 -
Dec. 16, 1994
Eligibility
Status: Closed With Output
Start Date: Nov. 3, 1994
End Date: Dec. 16, 1994
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Dec. 16, 1994 -
June 16, 1995
Compliance Review
Status: Closed With Output
Start Date: Dec. 16, 1994
End Date: June 16, 1995
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary, Mechanism chose not to monitor
Closed
June 30, 1995
Timeline
Documents
Involved Groups
Name | Complaints | Group Type |
---|---|---|
WAFED | 1 | Local CSO |
Alliance for Energy | 1 | Unknown |
Arun Concerned Group | 1 | Unknown |
Commitments