Barrage Réservoir de Lom Pangar - Nachtigal Hydropower Plant | Accountability Console
Complaints IAMs Register Login

Loading...

Barrage Réservoir de Lom Pangar - Nachtigal Hydropower Plant

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 359

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 526

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 343

Browse Complaints

Description

A local cooperative lodged a complaint raising concerns about inadequate consultation and information sharing about the adverse environmental and social impacts of two hydropower projects, Lom Pangar and Nachtigal. The complaint concerns 41 villages situated between the two dams. The complainant alleged that the environmental and social impact assessments only addressed the impacts upstream of the Lom Pangar dam, neglecting the downstream impacts, which include effects on the health and livelihoods of sand miners and fishermen.

Complaint Stages

Filing

Aug. 30, 2022

Filing

Status:

Start Date: Aug. 30, 2022

Registration

Aug. 30, 2022 -

Oct. 13, 2022

Registration

Status: Closed With Output

Start Date: Aug. 30, 2022

End Date: Oct. 13, 2022

Eligibility

Oct. 13, 2022 -

April 18, 2023

Eligibility

Status: Closed With Output

Start Date: Oct. 13, 2022

End Date: April 18, 2023

Dispute Resolution

Dispute Resolution

Status:

Start Date:

Compliance Review

Compliance Review

Status:

Start Date:

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Monitoring

Status:

Start Date:

Closed

Not Closed

Timeline