Corridor 10 Highway E-75

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Corridor 10 Highway E-75

Investments: EIB

Client:

Support: Loans

Country: Serbia

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2011/08

Date Filed: May 4, 2011

Date Closed: July 25, 2012

Status: Closed With Outputs

Description

The complaint concerns essentially that an alternative trajectory for the highway section, as proposed by the Leskovac local Government had not been selected. The said alternative trajectory had been prepared by the Traffic Institute (CIP) and would cost EUR 11m less than the alternative which had been selected and would not require the construction of a tunnel. In addition, the complaint concerned a lack of public consultations on the project and the fact that the Project had never been presented to the local government of Leskovac which therefore had not given its consent. The City Assembly of Leskovac had informed the Serbian Government and the ministries and Public Roads’ services concerned, in 2008, that selecting such an expensive alternative for the project, in opposition to the choice of the local Leskovas’ authorities, would constitute a breach of the national law.

Complaint Stages

Filing

May 4, 2011

Filing

Status:

Start Date: May 4, 2011

Registration

May 4, 2011 -

May 4, 2011

Registration

Status: Closed With Output

Start Date: May 4, 2011

End Date: May 4, 2011

Eligibility

May 4, 2011 -

May 18, 2011

Eligibility

Status: Closed With Output

Start Date: May 4, 2011

End Date: May 18, 2011

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage; Unknown

Compliance Review

May 18, 2011 -

July 25, 2012

Compliance Review

Status: Closed With Output

Start Date: May 18, 2011

End Date: July 25, 2012

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage; Outside of mandate, Bank not found to be responsible party

Closed

July 25, 2012

Timeline

Involved Groups

Name Complaints Group Type
City of Leskovac Assembly 1 Local Community Org