Corridor Vc 2 (Request #3)
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Corridor Vc 2 Project
Investments: EBRD 47372
Client: Motorways of the Federation of Bosnia and Herzegovina (FBHM), State of Bosnia and Herzegovina, Government of the Federation of Bosnia and Herzegovina
Support: Loans
Country: Bosnia and Herzegovina
Complaint
IAM: Independent Project Accountability Mechanism (IPAM)
ID: 2023/08
Date Filed: July 13, 2023
Status: Active
Description
Complaint Stages
Filing
July 13, 2023
Filing
Status:
Start Date: July 13, 2023
Registration
July 13, 2023 -
Aug. 24, 2023
Registration
Status: Closed With Output
Start Date: July 13, 2023
End Date: Aug. 24, 2023
Eligibility
Aug. 24, 2023 -
Feb. 2, 2024
Eligibility
Status: Closed With Output
Start Date: Aug. 24, 2023
End Date: Feb. 2, 2024
Dispute Resolution
Feb. 2, 2024
Dispute Resolution
Status: In Progress
Start Date: Feb. 2, 2024
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Dispute Resolution in progress
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Complaint not yet reached stage, Dispute Resolution in progress
Closed
Not Closed
Timeline
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Corridor Vc 2 Project | EBRD IPAM | Bosnia and Herzegovina | 13/07/2020 | Closed With Outputs Outside Process |
Corridor Vc 2 (Request #2) | EBRD IPAM | Bosnia and Herzegovina | 06/06/2023 | Closed Without Outputs |