Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Greater Beirut Water Supply Project
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 538
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Pollution
Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.
Complaints with this Issue: 229
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Greater Beirut Water Supply Project
Investments: WB P103063
Client: Council for Development and Reconstruction, Lebanese Republic, Government of Lebanon
Support: Loans
Country: Lebanon
Complaint Stages
Filing
Nov. 4, 2010
Filing
Status:
Start Date: Nov. 4, 2010
Registration
Nov. 4, 2010 -
Nov. 10, 2010
Registration
Status: Closed With Output
Start Date: Nov. 4, 2010
End Date: Nov. 10, 2010
Eligibility
Nov. 10, 2010 -
March 8, 2011
Eligibility
Status: Closed With Output
Start Date: Nov. 10, 2010
End Date: March 8, 2011
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Addressed outside process, Matter resolved outside mechanism
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
April 30, 2013
Timeline
Documents
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Water Supply Augmentation Project, Greater Beirut Water Supply Project and its Additional Financing | WB Panel | Lebanon | 06/08/2018 | Closed Without Outputs |