Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Integrated Citarum Water Resources Management Investment Program
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Sectors
Conservation and environmental protection
Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.
Complaints in this Sector: 62
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Integrated Citarum Water Resources Management Investment Program
Investments: ADB
Client:
Support: Loans
Country: Indonesia
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: Dec. 8, 2009
Date Closed: Jan. 31, 2010
Status: Closed Without Outputs
Complaint Stages
Filing
Dec. 8, 2009
Filing
Status:
Start Date: Dec. 8, 2009
Registration
Dec. 8, 2009 -
Dec. 11, 2009
Registration
Status: Closed With Output
Start Date: Dec. 8, 2009
End Date: Dec. 11, 2009
Eligibility
Dec. 11, 2009 -
Jan. 31, 2010
Dispute Resolution
Not Undertaken
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Jan. 31, 2010
Timeline
Involved Groups
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Integrated Citarum Water Resources Management Investment Program 2 | ADB SPF CRP | Indonesia | 04/01/2011 | Closed With Outputs |