Mining Infrastructure Investment Support and Mining Infrastructure Support - Additional Financing | Accountability Console
Complaints IAMs Register Login

Loading...

Mining Infrastructure Investment Support and Mining Infrastructure Support - Additional Financing

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 336

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 495

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 366

Browse Complaints

Sectors

Extractives (oil, gas, mining)

Description: Project relates to the extractive industries, including oil, gas, and mining. Examples may include mines, drilling operations, pipelines, and the associated legal frameworks.

Complaints in this Sector: 199

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 865

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 167

Browse Complaints

Project

Name: Mining Infrastructure Investment Support

Investments: WB P145439

Client:

Support:

Country: Mongolia

Complaint

IAM: Inspection Panel (Panel)

ID: 123

Date Filed: April 2, 2018

Date Closed: May 11, 2018

Status: Closed Without Outputs

Description

On April 2, 2018, the Inspection Panel received the Request for Inspection related to Mongolia Mining Infrastructure Investment Support Project and its Additional Financing (MINIS). The Request was submitted by the Rivers with Boundaries Coalition, Rivers without Boundaries Mongolia and a local NGO in Russia, the latter of which asked for confidentiality. They claimed potential environmental and social harm caused by the financing of impact assessments and feasibility studies of two subprojects financed by MINIS, as well as concerns related to lack of consultation and disclosure of information. Since the Request concerned an issue on which the Panel made a recommendation in 2017, the Panel had to assess whether information provided by the Requesters and Bank Management constituted new evidence or circumstances. The Panel said it did not consider this to be the case, and issued a Notice of Non-Registration for this Request on May 11, 2018.

Complaint Stages

Filing

April 2, 2018

Filing

Status:

Start Date: April 2, 2018

Registration

April 2, 2018 -

May 11, 2018

Registration

Status: Closed With Output

Explanation: Issues previously raised, Same issues raised in prior complaint

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

May 11, 2018

Timeline