Mongolia Mining Infrastructure Investment Support (P118109) and Mining Infrastructure Investment Support - Additional Financing
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Cultural heritage
Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.
Complaints with this Issue: 120
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 408
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Complaint
ID: 102
Date Filed: Feb. 10, 2015
Date Closed: July 27, 2017
Status: Closed Without Outputs
Complaint Stages
Filing
Feb. 10, 2015
Filing
Status:
Start Date: Feb. 10, 2015
Registration
Feb. 10, 2015 -
March 27, 2015
Registration
Status: Closed With Output
Start Date: Feb. 10, 2015
End Date: March 27, 2015
Eligibility
March 27, 2015 -
July 13, 2017
Eligibility
Status: Closed With Output
Explanation: Addressed outside process, Management is addressing or has addressed concerns
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
July 27, 2017
Timeline
Documents
Involved Groups
Name | Complaints | Group Type |
---|---|---|
Greenpeace Russia | 1 | International CSO |
Rivers Without Boundaries | 2 | International CSO |
Bank Information Center (BIC) | 30 | International CSO |