North-South Corridor (Kvesheti-Kobi) Road Project
Issues
Cultural heritage
Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.
Complaints with this Issue: 120
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Georgia: North-South Corridor (Kvesheti-Kobi) Road Project
Investments: ADB 3803
Client: Government of Georgia, Ministry of Regional Development and Infrastructure of Georgia
Support: Loans
Country: Georgia
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
ID: 2019/2
Date Filed: Oct. 16, 2019
Date Closed: Jan. 24, 2020
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Oct. 16, 2019
Filing
Status:
Start Date: Oct. 16, 2019
Registration
Oct. 16, 2019 -
Nov. 19, 2019
Registration
Status: Closed With Output
Start Date: Oct. 16, 2019
End Date: Nov. 19, 2019
Eligibility
Nov. 19, 2019 -
Jan. 24, 2020
Eligibility
Status: Closed With Output
Explanation: Filer Issue, Not filed by project affected people
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Jan. 24, 2020
Timeline
Documents
Name | Category | Description |
---|---|---|
Complaint | Filing | |
Complaint | Filing | |
Management Action Plan | Management Action Plan |