Reconquista River Basin Environmental Sanitation Program- Request IV | Accountability Console
Complaints IAMs Register Login

Loading...

Reconquista River Basin Environmental Sanitation Program- Request IV

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 359

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 525

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 213

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-BID-AR-2022-0187

Date Filed: June 1, 2022

Date Closed: June 7, 2022

Status: Closed Without Outputs

Description

The Request describes potential harm to the living conditions of the residents of the Moreno district in the province of Buenos Aires, Argentina. The damages are a consequence of unfinished work on a sewer network project. The Request also reports on the lack of communication and access to information for residents of the area, who express that the public information about the project is insufficient to clarify the future of the work that was already scheduled to be completed.

Complaint Stages

Filing

June 1, 2022

Filing

Status:

Start Date: June 1, 2022

Registration

June 1, 2022 -

June 7, 2022

Registration

Status: Closed With Output

Explanation: Good faith requirement not met

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

June 7, 2022

Timeline