Reconquista River Sanitation Environmental Program - Request V | Accountability Console
Complaints IAMs Register Login

Loading...

Reconquista River Sanitation Environmental Program - Request V

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 359

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 526

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 387

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 226

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Community capacity and development

Description: Project relates to programs targeted at training, capacity-building, and/or enabling public participation for specific groups within the community.

Complaints in this Sector: 112

Browse Complaints

Conservation and environmental protection

Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.

Complaints in this Sector: 62

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 964

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Description

The Request describes potential harm to the quality of life and access to public utilities of the group of Requesters due to the construction and distribution of sewer pipelines and water collectors, which are part of the Environmental Sanitation Program. Specifically, they allege that the works were abruptly interrupted, resulting in streets with wrecked sidewalks and the suspension of services. In addition, they assert that their environment has been degraded by the noise and the presence of rubble and waste derived from the cessation of the construction. In the same way, the Requesters claim economic harm since they have been bearing the costs of fixing sidewalks, pumping water, and cleaning the spaces, which are derived from the suspension of services. The Request also mentions potential non-compliance with the Bank's Relevant Operational Policies due to the lack of public information on the timeframe and conclusion of the project. Additionally, since the contractor in charge of the works declared bankruptcy, the information regarding the bidding process is insufficient and unavailable. This Request is directly linked to compliant MICI-BID-AR-2022-0187.

Complaint Stages

Filing

July 8, 2022

Filing

Status:

Start Date: July 8, 2022

Registration

July 8, 2022 -

July 13, 2022

Registration

Status: Closed With Output

Start Date: July 8, 2022

End Date: July 13, 2022

Eligibility

July 13, 2022 -

Sept. 22, 2022

Eligibility

Status: Closed With Output

Start Date: July 13, 2022

End Date: Sept. 22, 2022

Dispute Resolution

Sept. 22, 2022

Dispute Resolution

Status: In Progress

Start Date: Sept. 22, 2022

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Dispute Resolution in progress

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Dispute Resolution in progress

Closed

Not Closed

Timeline

Involved Groups

Name Complaints Group Type
Leonardo Filippini, Federal Prosecutor of Moreno 1 Other