Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Rivne Kyiv High Voltage Line
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 353
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Rivne Kyiv High Voltage Line
Investments: EBRD
Client:
Support: Loans
Country: Ukraine
Complaint
IAM: Project Complaint Mechanism (PCM)
ID: 2012/02
Date Filed: Jan. 10, 2012
Date Closed: Sept. 30, 2013
Status: Closed With Outputs
Complaint Stages
Filing
Jan. 10, 2012
Filing
Status:
Start Date: Jan. 10, 2012
Registration
Jan. 10, 2012 -
Jan. 17, 2012
Registration
Status: Closed With Output
Start Date: Jan. 10, 2012
End Date: Jan. 17, 2012
Eligibility
Jan. 17, 2012 -
Nov. 12, 2012
Eligibility
Status: Closed With Output
Start Date: Jan. 17, 2012
End Date: Nov. 12, 2012
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Nov. 12, 2012 -
Sept. 12, 2013
Compliance Review
Status: Closed With Output
Start Date: Nov. 12, 2012
End Date: Sept. 12, 2013
Has Compliance Report: Yes
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Sept. 30, 2013
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
National Ecological Centre of Ukraine | 3 | Local CSO |