São José dos Campos Urban Structuring Program

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Property damage

Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.

Complaints with this Issue: 169

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: São José dos Campos Urban Structuring Program

Investments: IDB BR-L1160

Client:

Support: Loans

Country: Brazil

Complaint

IAM: Independent Consultation and Investigation Mechanism (MICI)

ID: MICI-BID-BR-2017-0128

Date Filed: Dec. 11, 2017

Date Closed: Dec. 15, 2017

Status: Closed Without Outputs

Description

The Request raises potential harm to the Requesters property caused by multiple overflows of the Círrego Cambuí River. The Requesters allege that these harms could be caused by the lack of complementary works needed, from their perspective, before the construction of the Cambuí road corridor that is part of the Program. Also, the Request shows the Requesters concern for the environmental impact that the channeling of the Círrego Cambuí River could cause.

Complaint Stages

Filing

Dec. 11, 2017

Filing

Status:

Start Date: Dec. 11, 2017

Registration

Dec. 11, 2017 -

Dec. 15, 2017

Registration

Status: Closed With Output

Explanation: Good faith requirement not met

Eligibility

Not Undertaken

Eligibility

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Start Date: None

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Start Date: None

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Start Date: None

Closed

Dec. 15, 2017

Timeline