South-West Roads: Western Europe-Western China International Transit Corridor Project (CAREC 1b & 6b)
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 363
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 538
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 345
Property damage
Description: Complaint raises concerns about specific harm to property, including buildings, land, or property value. Concerns related to physical or economic displacement, pollution, or community health and safety are not included.
Complaints with this Issue: 169
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Investments: WB P099270
Client: Ministry of Investments and Development, The Republic of Kazakhstan, The Republic of Kazakhstan
Support: Loans
Country: Kazakhstan
Complaint
ID: 150
Date Filed: Dec. 24, 2020
Date Closed: April 26, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Dec. 24, 2020
Filing
Status:
Start Date: Dec. 24, 2020
Registration
Dec. 24, 2020 -
Feb. 16, 2021
Registration
Status: Closed With Output
Start Date: Dec. 24, 2020
End Date: Feb. 16, 2021
Eligibility
Feb. 16, 2021 -
April 26, 2021
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
April 26, 2021