Tbilisi Railway Bypass 1
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 537
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 994
Project
Name: Tbilisi Railway Bypass
Investments: EBRD 40173
Client: Georgian Railway LLC
Support: Loans
Country: Georgia
Complaint
IAM: Project Complaint Mechanism (PCM)
ID: 2011/01
Date Filed: March 7, 2011
Date Closed: July 31, 2012
Status: Closed With Outputs
Complaint Stages
Filing
March 7, 2011
Filing
Status:
Start Date: March 7, 2011
Registration
March 7, 2011 -
March 14, 2011
Registration
Status: Closed With Output
Start Date: March 7, 2011
End Date: March 14, 2011
Eligibility
March 14, 2011 -
Sept. 19, 2011
Eligibility
Status: Closed With Output
Start Date: March 14, 2011
End Date: Sept. 19, 2011
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Sept. 19, 2011 -
July 19, 2012
Compliance Review
Status: Closed With Output
Start Date: Sept. 19, 2011
End Date: July 19, 2012
Has Compliance Report: Yes
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
July 31, 2012
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
CEE Bankwatch Network | 41 | International CSO |
Green Alternative | 22 | Local CSO |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Tbilisi Railway Bypass 2 | EBRD PCM | Georgia | 07/03/2011 | Closed With Outputs |
Tbilisi Railway Bypass 3 | EBRD PCM | Georgia | 08/03/2011 | Closed With Outputs |
Tbilisi Railway Bypass 4 | EBRD PCM | Georgia | 16/03/2011 | Closed Without Outputs |