Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Urban development project, North Africa (Zenata, Morocco)
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 551
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1094
Complaint
IAM: Environmental and Social Complaints Mechanism (ESCM)
ID: None
Date Filed: Jan. 8, 2020
Date Closed: July 21, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Jan. 8, 2020
Filing
Status:
Start Date: Jan. 8, 2020
Registration
Jan. 8, 2020 -
Jan. 8, 2020
Registration
Status: Closed With Output
Start Date: Jan. 8, 2020
End Date: Jan. 8, 2020
Eligibility
Jan. 8, 2020 -
July 21, 2021
Eligibility
Status: Closed With Output
Explanation: Mechanism deemed involvement unnecessary; Addressed outside process; Outside of mandate; Outside of mandate, Bank not found to be responsible party
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
July 21, 2021
Timeline