Use Document search to find words or phrases in any publicly-available complaint documentation, including complaint filings, eligibility determinations, appraisals, agreements, compliance reports, monitoring reports, and more. Each result links back to its relevant complaint as well as the document itself. Contact us if you have any questions or need any help.

Search Terms

Filter By:

Clear

286 Results

Top Results By:

Show All

  1. Complaint > Electricity Expansion Project

    Registration: Notice of Registration (English)

    ...Cash Compensation The Requesters add that some households received a newly built house and cash compensation of"not less than Ksh. 195,000." 1 They state that this is based on "corruption, nepotism, ethnicity and religious ground." Retaliation Finally, they note that on October 23, 2014, the RAP Implementation Committee (RAPIC) had a meeting and tried by all means possible to stop the complaining process. The Requesters assert that there are several correspondences and letters ex...

    WB Inspection Panel - Kenya - 2014
  2. Complaint > Paraguay/Argentina Reform Project for the Water and Telecommunication Sectors, SEGBA V Power Distribution Project (Yacyreta)

    Management Action Plan: 26-Second Management Progress Report-25 October 2005

    ...compensation is large and expanding. In addition, cash payments may also undermine productive programs that EBY or local governments m a y wish to promote. Bank missions have made these points several times including in the rehabilitation workshop held in April 2005, and most recently with the Paraguayan authorities in early September 2005. To date, however, EBY and the authorities continue to rely o n cash compensation as a method o f rehabilitation. 33. Even in a cash-dominate...

    WB Inspection Panel - Argentina, Paraguay - 2002
  3. Complaint > Oyu Tolgoi-01/Khanbogd

    Agreement: English

    ...Compensation agreement and criteria for determining impacts and compensations are inappropriate • These two agreements could not be the proper response to stop or/and mitigate the negative impacts • Declining livelihoods, loss of income sources • Loss of livestock, decreasing livestock productivity, declining livestock health • Water depletion • Pastureland loss/deficiency, degradation (dust) • Compensation agr...

    IFC Compliance Advisor/Ombudsman - Mongolia - 2013
  4. Complaint > Paraguay/Argentina Reform Project for the Water and Telecommunication Sectors, SEGBA V Power Distribution Project (Yacyreta)

    Management Action Plan: 26-Third Management Progress Report-20 December 2006

    ...cash Bank continued to advise EBY that cash compensation i s not a satisfactory means, nor i s compensation i s not a fully satisfactory means, nor i s principal occupation the sole criterion for income principal occupation the sole criterion for income restoration. restoration (including in June, September, and December 2004; at the rehabilitation workshop held ...

    WB Inspection Panel - Argentina, Paraguay - 2002
  5. Complaint > Private Power Generation Project

    Management Action Plan: 44-Third Management Progress Report

    ...cash compensation, 300 households continued to use the cash to avail of agricultural programs (including inputs and market and group cooperatives); some 214 received, in addition to the cash support, some fisheries inputs (fishing gear, boats, fish nets distributed in 2011); and 100 households participated in 2011 in the livelihood training workshops. 24. The focus group meetings, held between February and October 2011, noted some of the problems faced by PAPs. These include, among others, c...

    WB Inspection Panel - Uganda - 2007
  6. Complaint > Smallholder Agriculture Development Project

    Compliance Report: 62-Investigation Report (English)

    ...Cash Economy 108. The transition from a subsistence economy to a market economy is one of the key development challenges for the whole country, and is very much the context of the SADP. 109. Some observers believe that subsistence agriculture underpins the Papua New Guinea cash economy. They maintain that even though the production and sale of cash crops is an important source of income at both the national and household levels, cash crops should not 124 PAD, p. 18. 1...

    WB Inspection Panel - Papua New Guinea - 2009
  7. Complaint > Power Development Project

    Registration: 87-Notice of Registration (English)

    ...cash compensation." According to the Request, complainants want the transmission line to be realigned or that they be offered substitute land or ''fair and adequate compensation." Moreover, the Request states that land-based resettlement options should be preferred for persons whose livelihoods are land-based, and cash compensation may not be an appropriate compensation strategy in such cases. Inadequate Study ofAlternatives The Request states that complainants have repeatedly req...

    WB Inspection Panel - Nepal - 2013
  8. Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit

    Eligibility: Inspection Panel Report and Recommendation

    ...cash compensation was already failing in case of the Hill Route and that the Valley Route people will have even less ability to deal with cash because they are poorer: this raises whole question of land for land compensation and actual implementation. According to the Request the law is basically limited to cash compensation and PAFs are not being informed of a land ~ p t i o n . ~The ’ Requesters are not aware L that any socio-economic survey has been done to determine value o...

    WB Inspection Panel - Nepal - 1994
  9. Complaint > Salala Rubber Corporation-01/Margibi and Bong

    Filing: CAO Complaint - Liberia - Salala Rubber Corporation 01

    ...cash compensation where appropriate; and (ii) provid[ing] relocation assistance” suited to our needs.300 “Alternative housing and/or cash compensation will be made available prior to relocation. New resettlement sites built for displaced persons will offer improved living conditions.”301 However, SRC never offered us any resettlement options, and certainly never furnished alternative housing and/or cash compensation before evicting us f...

    IFC Compliance Advisor/Ombudsman - Liberia - 2019
  10. Complaint > North-South Corridor (Kvesheti-Kobi) Road Project

    Monitoring: CRP 1st Annual Monitoring Report (English)

    ...cash compensation in order to further mitigate any negative project impacts, address vulnerability and support the livelihood of the affected persons. 30. The additional non-cash assistance includes employment opportunities, training to improve the skills of the affected persons for agriculture-based activities, business, financial management and tourism as well as improve the produce from their lands. The affected persons will also be engaged in awareness programs on the tourism industry,...

    ADB Special Project Facilitator and Compliance Review Panel - Georgia - 2023
  11. Complaint > Giza North Power Project

    Eligibility: 85-Eligibility Report and Recommendation (English)

    ...compensation for the impacts of the dust and the construction of the wall surrounding the power plant. 52. While the farmers state that the groundwater level continues to be low, Management affirms that the original level has been restored. Further, the Panel notes that the Management and CEPC officials view is that farmers received cash compensation and free piped water beyond the amounts estimated by the Cairo University study. 53. While the Panel is not in a position at ...

    WB Inspection Panel - Egypt - 2013
  12. Complaint > Petroleum Development and Pipeline Project, and Petroleum Environment Capacity Enhancement Project

    Management Response: 27-Management Response (English)

    ...compensation for crop losses due to temporary occupation of land during construction (which is not eligible for compensation under Cameroon law); and (iii) providing community compensation corresponding to the value of lost common property resources and in recognition of the general disturbance caused by the Pipeline Project to neighboring communities. Government compensation is provided in cash only, whereas COTCO supplemental individual compensation is provided in cash or in kind according to ...

    WB Inspection Panel - Cameroon - 2002
  13. Complaint > Petroleum Development and Pipeline Project, Management of the Petroleum Economy Project, and Petroleum Sector Management Capacity Building Project

    Management Response: 22-Management Response (English)

    ...compensation choices (cash or in-kind) were documented. Receipts were signed for all compensation paid and a grievance process was in place for affected people to voice their concerns. This process will continue in a consultative manner and will be thoroughly documented as compensation proceeds. 99. The list of all villages where cash or in-kind compensation was paid is presented in Annex F. A total of 248 million CFAF (approximately US$350,000) has been paid out as compensation, 22 percent...

    WB Inspection Panel - Chad - 2001
  14. Complaint > Pan African Paper-01/Webuye

    Eligibility: Assessment Report, October 15, 2008

    ...Compensation for Relocation • Compensation for relocation from the Factory Site was handled by the Government of Kenya and the affected people were accordingly paid off and resettled elsewhere. There have been no claims for compensation of alleged work-related illnesses. - 15 -

    IFC Compliance Advisor/Ombudsman - Kenya
  15. Complaint > Arun III Proposed Hydroelectric Project and Restructuring of IDA Credit

    Management Response: Management Response (English)

    ...compensation, and all PAFs are being offered full cash compensation for their land. 23. Despite efforts t o minimize land acquisition, some families face permanent loss of land. The t y p e of compensation provided - cash versus land - depends on the significance o f land in the affected family's income-earning activities. However, the actual value o f compensation paid will be same whether it is paid in cash or in kind (land); all valuations are done according ...

    WB Inspection Panel - Nepal - 1994
  16. Complaint > Coal Sector Mitigation Project and Coal Sector Rehabitation Project

    Management Response: 23-Management Response (English)

    ...Compensation for lost assets 25 3.6.1 Compensation for privately held land – tenancy land 25 3.6.2 Compensation for privately held land - customary tenure 27 3.6.3 Compensation for common property resources 27 3.6.4 House compensation 28 3.7 Income restoration ...

    WB Inspection Panel - India - 2001
  17. Complaint > Second Urban Environment Sanitation Project

    Management Action Plan: 49-Third Management Progress Report (English)

    ...compensation for the 76 inhabited structures, as noted above. The DCA was amended to include the compensation payments and the GoG submitted an updated Kwabenya Plan for Compensation that was reviewed and accepted as satisfactory by the Bank. In addition, a RAP consultant was retained by the GoG to facilitate the dissemination of information to affected people about compensation for lost assets and eligibility 4 ...

    WB Inspection Panel - Ghana - 2007
  18. Complaint > Rehabilitation of the Railway in Cambodia Project

    Filing: Complaint

    ...compensation rates, 3) and provide retroactive compensation to affected people who have already received compensation “[i]f a need for adjustment is identified.”6 ADB further committed to review and address g. Despite these commitments and the ongoing dialogue with both Cambodian Resident Mission and regional ADB Operations staff over the past year, there has been no resolution of the most serious resettlement problems that have been brought to ADB’s attention. Notably, compensation rates...

    ADB Special Project Facilitator and Compliance Review Panel - Cambodia - 2011
  19. Complaint > Land Management and Administration Project

    Eligibility: 60-Eligibility Report (English)

    ...compensation options. These options were: cash compensation, relocation in a site many kilometers away, and, finally, onsite housing coupled with 4 Consistent with initial indications from the Requesters, the Panel redacted certain references in the Request for Inspection before issuing the Notice of Registration. Subsequently, the Panel received authorization from the Requesters to publish the more detailed information that is included in this Report and its Annexes. Annex 1 of Man...

    WB Inspection Panel - Cambodia - 2009
  20. Complaint > North-South Corridor (Kvesheti-Kobi) Road Project

    Compliance Report: CRP's Final Report (English)

    ...compensation entitlements in the LARPs include the cash value of crops; cash compensation for affected trees based on the expected yield of the tree multiplied by the number of years required to grow a tree of equivalent productivity; and cash compensation for loss of agricultural land at full replacement cost based on current market value. These entitlements are not adequate to restore the livelihoods of affected people who use land that is acquired for the Project for subsistence producti...