120 MW Malicounda Dual Fuel Power Project in Senegal

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 538

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 494

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Procurement

Description: Complaint raises concerns about the process for obtaining goods or services related to the project. Most IAMs cannot address procurement concerns.

Complaints with this Issue: 79

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Project

Name: 120 MW Malicounda Dual Fuel Power Project in Senegal

Investments: AfDB

Client: Senelec

Support: Loans

Country: Senegal

Complaint

IAM: Independent Recourse Mechanism (IRM)

ID: RQ 2022/01

Date Filed: Dec. 17, 2021

Status: Active

Description

The Complaint alleged that the implementaiton of the Project has failed to create and enforce a sufficient Resettlement Action Plan resulting in loss of land, housing plots, lack of compensation, and predetory practices in the purchase of land. Additionally, a lack of monitoring by the Bank has lead to a failure to meet operational safeguards for land aquisition, population displacement, compensation, and consultation.

Complaint Stages

Filing

Dec. 17, 2021

Filing

Status:

Start Date: Dec. 17, 2021

Registration

Dec. 17, 2021 -

Jan. 31, 2022

Registration

Status: Closed With Output

Start Date: Dec. 17, 2021

End Date: Jan. 31, 2022

Eligibility

Jan. 31, 2022 -

June 1, 2022

Eligibility

Status: Closed With Output

Start Date: Jan. 31, 2022

End Date: June 1, 2022

Dispute Resolution

June 1, 2022

Dispute Resolution

Status: In Progress

Start Date: June 1, 2022

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Dispute Resolution in progress

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Complaint not yet reached stage, Dispute Resolution in progress

Closed

Not Closed

Timeline