Paravani Hydro Power Plant

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 103

Browse Complaints

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 258

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 384

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 385

Browse Complaints

Sectors

Energy

Description:

Complaints in this Sector: 203

Browse Complaints

Infrastructure

Description:

Complaints in this Sector: 504

Browse Complaints

Project

Name: Paravani Hydro Power Plant

Investments: EBRD

Client:

Support: Equity, Loans

Country: Georgia

Complaint

IAM: Project Complaint Mechanism (PCM)

ID: 2012/010

Date Filed: Dec. 22, 2011

Status: Monitoring

Complaint Stages

Filing

Dec. 22, 2011

Filing

Status:

Start Date: Dec. 22, 2011

Registration

Dec. 22, 2011 -

Jan. 4, 2012

Registration

Status: Completed

Start Date: Dec. 22, 2011

End Date: Jan. 4, 2012

Eligibility

Jan. 4, 2012 -

Oct. 24, 2012

Eligibility

Status: Completed

Start Date: Jan. 4, 2012

End Date: Oct. 24, 2012

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Dispute resolution was not an option in this case

Compliance Review

Oct. 24, 2012 -

Jan. 24, 2014

Compliance Review

Status: Completed

Start Date: Oct. 24, 2012

End Date: Jan. 24, 2014

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Jan. 2, 2014

Monitoring

Status: In Progress

Start Date: Jan. 2, 2014

Closed

Not Closed

Timeline