Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Project
Name: Abidjan Urban Transport Project
Investments: AfDB
Client:
Support:
Country: Ivory Coast
Complaint
IAM: Independent Recourse Mechanism (IRM)
ID: 2018/2b
Date Filed: Dec. 17, 2018
Date Closed: Sept. 30, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
Dec. 17, 2018
Filing
Status:
Start Date: Dec. 17, 2018
Registration
Dec. 17, 2018 -
Dec. 28, 2018
Registration
Status: Closed With Output
Start Date: Dec. 17, 2018
End Date: Dec. 28, 2018
Eligibility
Dec. 28, 2018 -
March 11, 2019
Eligibility
Status: Closed With Output
Start Date: Dec. 28, 2018
End Date: March 11, 2019
Dispute Resolution
March 12, 2019 -
March 11, 2021
Dispute Resolution
Status: Closed Without Output
Explanation: Addressed outside process; Issues previously raised, Parallel proceedings
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Start Date: None
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Start Date: None
Closed
Sept. 30, 2021
Timeline
Documents
Name | Category | Description |
---|---|---|
Second Request | Filing |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Abidjan Urban Transport Project | AfDB IRM | Ivory Coast | 18/09/2018 | Closed With Outputs |
Abidjan Urban Transport Project | AfDB IRM | Ivory Coast | 26/12/2018 | Closed With Outputs |