Bangalore Metro Rail Project - Line R6

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 134

Browse Complaints

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 538

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 120

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Project

Name: Bangalore Metro Rail Project Line R6

Investments: EIB

Client:

Support:

Country: India

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2019/08

Date Filed: June 7, 2019

Date Closed: June 17, 2022

Status: Closed With Outputs

Description

In June 2019, a member of a congregation supported by a local NGO submitted a complaint alleging negative environmental and social impacts of the Bangalore Metro Rail project. Following a site visit by the dispute resolution team, the initial assessment report clarified some misunderstandings and proposed a dispute resolution process for the remaining allegations. Due to the COVID-19 pandemic, the process was carried out remotely with the support of two local facilitators.

Complaint Stages

Filing

June 7, 2019

Filing

Status:

Start Date: June 7, 2019

Registration

June 7, 2019 -

June 13, 2019

Registration

Status: Closed With Output

Start Date: June 7, 2019

End Date: June 13, 2019

Eligibility

June 13, 2019 -

Oct. 30, 2019

Eligibility

Status: Closed With Output

Start Date: June 13, 2019

End Date: Oct. 30, 2019

Dispute Resolution

Oct. 30, 2019 -

June 24, 2021

Dispute Resolution

Status: Closed With Output

Start Date: Oct. 30, 2019

End Date: June 24, 2021

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

June 24, 2021 -

June 17, 2022

Monitoring

Status: Closed With Output

Start Date: June 24, 2021

End Date: June 17, 2022

Closed

June 17, 2022

Timeline

Involved Groups

Name Complaints Group Type
local NGO 1 Local CSO