Corridor Vc in FBH - Part 3 Project

Issues

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Corruption/fraud

Description: Complaint raises concerns about corruption and/or fraud related to the project. Most IAMs cannot address corruption or fraud concerns.

Complaints with this Issue: 30

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 120

Browse Complaints

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 494

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Description

The requesters, the Community of Royal Vineyards (Carski Vinogradi) Malo Polje, Kocine, allege that the current alignment of the motorway funded under the Corridor Vc in FBH – Part 3 (49058) project will adversely impact the community and the environment. Particularly they claim that the current alignment has disregarded the welfare of refugee returnees, has failed to adequately assess the impact on the region both as regards its fertility and the social and cultural implications. The Requesters allege that no consideration of impacts has taken place and that there has been no transparency nor public participation. They are requesting a compliance review.

Complaint Stages

Filing

Jan. 6, 2020

Filing

Status:

Start Date: Jan. 6, 2020

Registration

Jan. 6, 2020 -

Oct. 1, 2020

Registration

Status: Closed With Output

Start Date: Jan. 6, 2020

End Date: Oct. 1, 2020

Eligibility

Oct. 1, 2020 -

Jan. 6, 2021

Eligibility

Status: Closed With Output

Start Date: Oct. 1, 2020

End Date: Jan. 6, 2021

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not desired by complainant, Complainant chose not to have dispute resolution

Compliance Review

Jan. 6, 2021 -

Jan. 11, 2024

Compliance Review

Status: Closed With Output

Start Date: Jan. 6, 2021

End Date: Jan. 11, 2024

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Jan. 11, 2024

Monitoring

Status: In Progress

Start Date: Jan. 11, 2024

Closed

Not Closed

Timeline