Irrigation System Enhancement Project (First Request)
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 538
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Project
Name: Irrigation System Enhancement Project
Investments: WB P127759
Client: Republic of Armenia, Water Sector Development unit PIU
Support:
Country: Armenia
Description
Complaint Stages
Filing
March 18, 2016
Filing
Status:
Start Date: March 18, 2016
Registration
March 18, 2016 -
April 26, 2016
Registration
Status: Closed With Output
Start Date: March 18, 2016
End Date: April 26, 2016
Eligibility
April 26, 2016 -
July 20, 2017
Eligibility
Status: Closed With Output
Explanation: Addressed outside process, Management is addressing or has addressed concerns
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Start Date: None
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Start Date: None
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Start Date: None
Closed
July 20, 2017
Timeline
Documents
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Irrigation System Enhancement Project (Second Request) | WB Panel | Armenia | 03/03/2016 | Closed With Outputs Outside Process |