Mumbai Metro Line 3 Project | Accountability Console
Complaints IAMs Register Login

Loading...

Mumbai Metro Line 3 Project

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 134

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Project

Name: Mumbai Metro Line 3 Project

Investments: JICA

Client:

Support:

Country: India

Complaint

IAM: Examiner for Environmental Guidelines (EEG)

ID: india_02

Date Filed: Aug. 30, 2015

Status: Closed Without Outputs

Complaint Stages

Filing

Aug. 30, 2015

Filing

Status:

Start Date: Aug. 30, 2015

Registration

Aug. 30, 2015 -

Sept. 7, 2015

Registration

Status: Closed With Output

Start Date: Aug. 30, 2015

End Date: Sept. 7, 2015

Eligibility

Sept. 7, 2015 -

Oct. 6, 2015

Eligibility

Status: Closed With Output

Explanation: Addressed outside process, Management is addressing or has addressed concerns

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Not Closed

Timeline