Reconquista River Basin Environmental Sanitation Program- Request III | Accountability Console
Complaints IAMs Register Login

Loading...

Reconquista River Basin Environmental Sanitation Program- Request III

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Community capacity and development

Description: Project relates to programs targeted at training, capacity-building, and/or enabling public participation for specific groups within the community.

Complaints in this Sector: 112

Browse Complaints

Conservation and environmental protection

Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.

Complaints in this Sector: 62

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Description

The Requesters allege potential environmental and health damages linked to the intervention of the Reconquista river as contemplated in the Program. Decline of the quality of water and bad environmental conditions caused by the dumping of pollutants. Dismantling of the drainage and piping system, including water systems, sewage drains, and opening of streets related to the Program. Impact on safety caused by increased risk of flooding. Finally, the Request alleges a lack of relevant information about the Project and deficient public consultations with the impacted population.

Complaint Stages

Filing

May 7, 2019

Filing

Status:

Start Date: May 7, 2019

Registration

May 7, 2019 -

May 14, 2019

Registration

Status: Closed With Output

Start Date: May 7, 2019

End Date: May 14, 2019

Eligibility

May 14, 2019 -

Aug. 23, 2019

Eligibility

Status: Closed With Output

Start Date: May 14, 2019

End Date: Aug. 23, 2019

Dispute Resolution

Oct. 21, 2019 -

Dec. 16, 2019

Dispute Resolution

Status: Closed With Output

Start Date: Oct. 21, 2019

End Date: Dec. 16, 2019

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint settled in Dispute Resolution so Compliance Review not offered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Dec. 16, 2019

Monitoring

Status: In Progress

Start Date: Dec. 16, 2019

Closed

Not Closed

Timeline