Regional Mombasa Port Access Road | Accountability Console
Complaints IAMs Register Login

Loading...

Regional Mombasa Port Access Road

Issues

Displacement (physical and/or economic)

Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.

Complaints with this Issue: 440

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 191

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 865

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 167

Browse Complaints

Project

Name: Regional Mombasa Port Access Road

Investments: EIB 20140546

Client: Kenya National Highways Authority

Support:

Country: Kenya

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2017/27

Date Filed: June 30, 2017

Date Closed: Dec. 11, 2019

Status: Closed With Outputs

Description

On 30 June 2017, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging concerns about negative impact on business in relation to the project ‰ÛÏRegional Mombasa Port Access Road" (2014-0546), Kenya.

Complaint Stages

Filing

June 30, 2017

Filing

Status:

Start Date: June 30, 2017

Registration

June 30, 2017 -

July 7, 2017

Registration

Status: Closed With Output

Start Date: June 30, 2017

End Date: July 7, 2017

Eligibility

July 7, 2017 -

June 23, 2019

Eligibility

Status: Closed With Output

Start Date: July 7, 2017

End Date: June 23, 2019

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Unknown

Compliance Review

June 23, 2019 -

Nov. 29, 2019

Compliance Review

Status: Closed With Output

Start Date: June 23, 2019

End Date: Nov. 29, 2019

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Monitoring

Status:

Explanation: Unknown

Closed

Dec. 11, 2019

Timeline