South-West Roads: Western Europe-Western China International Transit Corridor (CAREC-1b & 6b) (Second Request)
Issues
Biodiversity
Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.
Complaints with this Issue: 134
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 538
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 494
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 486
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 995
Complaint Stages
Filing
June 15, 2011
Filing
Status:
Start Date: June 15, 2011
Registration
June 15, 2011 -
Aug. 17, 2011
Registration
Status: Closed With Output
Start Date: June 15, 2011
End Date: Aug. 17, 2011
Eligibility
Aug. 17, 2011 -
Oct. 18, 2011
Eligibility
Status: Closed With Output
Start Date: Aug. 17, 2011
End Date: Oct. 18, 2011
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Addressed outside process, Matter resolved outside mechanism
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
Oct. 31, 2011
Timeline
Documents
Involved Groups
Name | Complaints | Group Type |
---|---|---|
National Analytical Information Resource (NAIR) | 1 | Local CSO |