Trans Adriatic Pipeline

Issues

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Extractives (oil, gas, mining)

Description: Project relates to the extractive industries, including oil, gas, and mining. Examples may include mines, drilling operations, pipelines, and the associated legal frameworks.

Complaints in this Sector: 201

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Project

Name: Trans Adriatic Pipeline

Investments: EIB 20140596

Client: Trans Adriatic Pipeline AG

Support:

Country: Italy

Complaint

IAM: Complaints Mechanism (CM)

ID: SG/E/2017/22/PR

Date Filed: June 26, 2017

Date Closed: Sept. 14, 2017

Status: Closed With Outputs Outside Process

Description

On 26 June 2017, the EIB Complaints Mechanism (EIB-CM) received a complaint alleging non-compliance with EU applicable regulatory framework in relation to the project "Trans Adriatic Pipeline" in Italy. The project concerns the financing and construction of the Trans Adriatic Pipeline (TAP), which is the western part of the Southern Gas Corridor that goes from the Greek/Turkish border to Italy through Albania.

Complaint Stages

Filing

June 26, 2017

Filing

Status:

Start Date: June 26, 2017

Registration

June 26, 2017 -

June 26, 2017

Registration

Status: Closed With Output

Start Date: June 26, 2017

End Date: June 26, 2017

Eligibility

June 26, 2017 -

June 30, 2017

Eligibility

Status: Closed With Output

Explanation: Inadequate information, Early-stage project; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Mechanism deemed involvement unnecessary; Case closed in earlier stage, Complaint was originally found ineligible or not registered; Addressed outside process, Matter resolved outside of mechanism; Forwarded to other body within bank, Mechanism forwarded complaint to management; Outside of mandate, Project not implemented

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Sept. 14, 2017

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage

Closed

Sept. 14, 2017

Timeline

Related Complaints