Water Supply Augmentation Project, Greater Beirut Water Supply Project and its Additional Financing | Accountability Console
Complaints IAMs Register Login

Loading...

Water Supply Augmentation Project, Greater Beirut Water Supply Project and its Additional Financing

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 134

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 537

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 120

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Water

Description: Complaint raises concerns about access to or availability of water. Concerns related to water pollution are not included.

Complaints with this Issue: 194

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 994

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Description

The Requesters expressed concern about the construction of the Bisri Dam on the Awwali River in the Bisri Valley in Lebanon, and claimed that the assessment of alternatives was inadequate. They alleged harm to natural habitats, forests, cultural heritage, agriculture, and water sources, as well as a lack of consultation and participation. The Requesters also were concerned about the geology and seismology of the project area.

Complaint Stages

Filing

Aug. 6, 2018

Filing

Status:

Start Date: Aug. 6, 2018

Registration

Aug. 6, 2018 -

Sept. 12, 2018

Registration

Status: Closed With Output

Start Date: Aug. 6, 2018

End Date: Sept. 12, 2018

Eligibility

Oct. 14, 2018 -

Dec. 6, 2018

Eligibility

Status: Closed With Output

Explanation: Mechanism deemed involvement unnecessary; Addressed outside process, Management is addressing or has addressed concerns

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Stage is not practiced by mechanism

Compliance Review

Not Undertaken

Compliance Review

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Has Compliance Report: No

Non-Compliance Found: No

Monitoring

Not Undertaken

Monitoring

Status: Not Undertaken

Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered

Closed

Dec. 6, 2018

Timeline