125 MW Coal-Fired Power Plant in Sendou | Accountability Console
Complaints IAMs Register Login

Loading...

125 MW Coal-Fired Power Plant in Sendou

Issues

Community health and safety

Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.

Complaints with this Issue: 363

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 538

Browse Complaints

Cultural heritage

Description: Complaint raises concerns about impacts on any type of tangible or intangible cultural heritage, including significant sites, unique environmental features, cultural knowledge, and traditional lifestyles.

Complaints with this Issue: 120

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Livelihoods

Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.

Complaints with this Issue: 345

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Sectors

Energy

Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.

Complaints in this Sector: 353

Browse Complaints

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Project

Name: 125 MW Coal-Fired Power Plant in Sendou

Investments: AfDB 46002-P-SN-F00-004

Client: Nykomb Synergetics (Sweden)

Support: Loans

Country: Senegal

Complaint

IAM: Independent Recourse Mechanism (IRM)

ID: RQ2016/2B

Date Filed: July 15, 2016

Status: Monitoring

Description

The Requestors called for CRMU to handle their complaint through both problem-solving and compliance review. During the preliminary review of this Request to determine if it meets the registration requirements of the Operating Rules and Procedures of the Independent Review Mechanism (IRM), CRMU received on 15 July 2016 the Second Request which was sent by two individuals, Mr. Cheikh Fadel Wade and Mr. Daouda Gueye on behalf of some other affected members of the communities in Bargny.Mr. Daouda challenged the representational authority of the First Requestors to act on behalf of all the PAPs. Standing on their own right, they requested to register their complaint for compliance review of the project. The two Requests raise similar issues with regard to the negative impacts of the Sendou coal power plant.

Complaint Stages

Filing

July 15, 2016

Filing

Status:

Start Date: July 15, 2016

Registration

July 12, 2016 -

Aug. 10, 2016

Registration

Status: Closed With Output

Start Date: July 12, 2016

End Date: Aug. 10, 2016

Eligibility

Aug. 10, 2016 -

April 3, 2017

Eligibility

Status: Closed With Output

Start Date: Aug. 10, 2016

End Date: April 3, 2017

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Dispute resolution was not an option in this case

Compliance Review

April 3, 2017 -

Jan. 31, 2019

Compliance Review

Status: Closed With Output

Start Date: April 3, 2017

End Date: Jan. 31, 2019

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

Jan. 31, 2019

Monitoring

Status: In Progress

Start Date: Jan. 31, 2019

Closed

Not Closed

Timeline