Project
Name: Abidjan Urban Transport Project
Investments: AfDB
Client:
Support:
Country: Ivory Coast
Complaint
IAM: Independent Recourse Mechanism (IRM)
ID: 2018/2c
Date Filed: Dec. 26, 2018
Date Closed: Sept. 30, 2021
Status: Closed With Outputs
Description
Complaint Stages
Filing
Dec. 26, 2018
Filing
Status:
Start Date: Dec. 26, 2018
Registration
Dec. 26, 2018 -
Dec. 28, 2018
Registration
Status: Closed With Output
Start Date: Dec. 26, 2018
End Date: Dec. 28, 2018
Eligibility
Dec. 28, 2018 -
March 11, 2019
Eligibility
Status: Closed With Output
Start Date: Dec. 28, 2018
End Date: March 11, 2019
Dispute Resolution
March 12, 2019 -
March 11, 2021
Dispute Resolution
Status: Closed With Output
Start Date: March 12, 2019
End Date: March 11, 2021
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Start Date: None
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary, Mechanism chose not to monitor
Closed
Sept. 30, 2021
Timeline
Documents
Name | Category | Description |
---|---|---|
Third Request | Filing |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Abidjan Urban Transport Project | AfDB IRM | Ivory Coast | 18/09/2018 | Closed With Outputs |
Abidjan Urban Transport Project | AfDB IRM | Ivory Coast | 17/12/2018 | Closed Without Outputs |