Contact Us
×Thank you for taking the time to help us improve the Console.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Loading...
Cairo Metro Line 3 (Phase 3)
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 495
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 440
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 865
Project
Name: Cairo Metro Line 3
Investments: EIB 20100613
Client: National Authority for Tunnels (NAT)
Support: Loans
Country: Egypt
Complaint
IAM: Complaints Mechanism (CM)
ID: SG/E/2017/10
Date Filed: March 2, 2017
Date Closed: March 31, 2020
Status: Monitoring
Description
Complaint Stages
Filing
March 2, 2017
Filing
Status:
Start Date: March 2, 2017
Registration
March 2, 2017 -
March 9, 2017
Registration
Status: Closed With Output
Start Date: March 2, 2017
End Date: March 9, 2017
Eligibility
March 9, 2017 -
Oct. 20, 2017
Eligibility
Status: Closed With Output
Start Date: March 9, 2017
End Date: Oct. 20, 2017
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Start Date: None
Compliance Review
Oct. 20, 2017 -
March 19, 2020
Compliance Review
Status: Closed Without Output
Start Date: Oct. 20, 2017
End Date: March 19, 2020
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
March 19, 2020
Monitoring
Status: In Progress
Start Date: March 19, 2020
Closed
March 31, 2020
Timeline
Related Complaints