Improving Solid Waste Management and Income Creation in Host Communities- Rehabilitation of Al Alake | Accountability Console
Complaints IAMs Register Login

Loading...

Improving Solid Waste Management and Income Creation in Host Communities- Rehabilitation of Al Alake

Issues

Biodiversity

Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.

Complaints with this Issue: 134

Browse Complaints

Consultation and disclosure

Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.

Complaints with this Issue: 538

Browse Complaints

Due diligence

Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.

Complaints with this Issue: 486

Browse Complaints

Environmental

Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.

Complaints with this Issue: 408

Browse Complaints

Human rights

Description: Complaint frames concerns using the language of human rights violations.

Complaints with this Issue: 66

Browse Complaints

Other

Description: Complaint raises concerns about impacts that do not fit in one of the other categories. Complaints about which there is no publicly available information regarding the issues raised are also included.

Complaints with this Issue: 219

Browse Complaints

Pollution

Description: Complaint raises concerns about releases of pollutants related to the project, including hazardous or non-hazardous chemicals, minerals, metals, pathogens, odors, noise, vibration, radiation, light, and heat.

Complaints with this Issue: 229

Browse Complaints

Sectors

Infrastructure

Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.

Complaints in this Sector: 995

Browse Complaints

Other

Description: Project relates to an industry that does not fit in one of the other sectors. Projects about which there is no publicly available information regarding the industry are also included.

Complaints in this Sector: 595

Browse Complaints

Regulatory Development

Description: Project relates specifically to development or reform of legal frameworks, including laws and regulations.

Complaints in this Sector: 169

Browse Complaints

Complaint

IAM: Social and Environmental Compliance Unit (SECU)

ID: SECU0007

Date Filed: June 5, 2018

Status: Monitoring

Description

The complainant alleges that after becoming aware of the construction of a waste management and transfer station in Jerash area, Jordan, they protested its establishment to avoid negative environmental and social impacts. The complainant sought documents to which they were entitled, such as the Environmental Impact Assessment, and claim to have been denied access by the UNDP Country Office. They sought to engage with UNDP as stakeholders on the project on the project and were rebuffed. The allegations state that the rejections from UNDP Jordan were accompanied by harassment and retaliation. Complainant notes that they are the recipient of a Global Environment Facility (GEF) small grant. The Complainant alleges that the waste management/transfer station appears to have been stopped, but that the failure of proper natural resource management by UNDP and damage to regional biodiversity remain major problems for the community.

Complaint Stages

Filing

June 5, 2018

Filing

Status:

Start Date: June 5, 2018

Registration

June 5, 2018 -

June 12, 2018

Registration

Status: Closed Without Output

Start Date: June 5, 2018

End Date: June 12, 2018

Eligibility

June 12, 2018 -

Aug. 28, 2018

Eligibility

Status: Closed With Output

Start Date: June 12, 2018

End Date: Aug. 28, 2018

Dispute Resolution

Not Undertaken

Dispute Resolution

Status: Not Undertaken

Explanation: Not offered by mechanism, Dispute resolution was not an option in this case

Compliance Review

Nov. 28, 2018 -

Dec. 6, 2019

Compliance Review

Status: Closed With Output

Start Date: Nov. 28, 2018

End Date: Dec. 6, 2019

Has Compliance Report: Yes

Non-Compliance Found: Yes

Monitoring

June 10, 2020

Monitoring

Status: In Progress

Start Date: June 10, 2020

Closed

Not Closed

Timeline